PROJECT COMPLETED: |
STATUS: |
CANAL LINING
Client: NATIONAL IRRIGATION AUTHORITY
Location/Address: Florida Blanca, Pampanga
Contract Time: 180 days
Date Start: December 15, 2006
Date: Completed: April 15, 2007
|
completed |
COMPLETION PAMPANGA POLICE OFFICE
Client: PHILIPPINE NATIONAL POLICE (CHIEF RFS 03)
Location/Address: Sto. Nino, City of San Fernando
Contract Time: 180 days
Date Start: July 2006
Date completed: December 2006
|
completed |
GUAGUA CENTRAL ELEMENTARY SCHOOL
AND SAN MATIAS ELEMENTARY SCHOOL
Client: DepEd School Building Project
Location/Address:Guagua,Pampanga
Contract Time: 120 days
Date Start: July 27,2006
Date Completed: November 24, 2006
|
completed |
CONSTRUCTION OF FREEFORT OIL-CBD PROJECT
Client:FREEFORT SERVICE CORP. SBMA
Contract Time: 65 days
Date Start : June 5,2006
Date Completed:cAugust 10, 2006
|
completed |
FENCING & BACKFILLING OF 1,000 SQ.M (1-M HIGH)
Client: Mr. Kazuo & Jocelyn Onodera
Location/Address: San Felife, San Fernando, Pampanga
Contract Time: 30 days
Date Start: April 01,2006
Date Completed: April 20, 2006
|
completed |
BOARDWALK,ROAD & DRAINAGE SYSTEM
Client: SCDC – Mr. Marianito Fernandes
Location/address: Pier 1 SBMA
Contract Time: 180 days
Date Start: October 2005
Date Completed: December 2006
|
completed |
VILLA PAULINA SUBDIVISION DEVELOPMENT
Client: ANROSvBUILDERS – Rosana Patawaran
Location/Address: Panipuan, Mexico, Pampanga
Contract Time: 365 days
Date start: March 02, 2005
Date Completed: February 25, 2006
|
completed |
FSC BOTON GAS STATION & CONVENIENCE STORE
Client: FREEPORT SERVICE CORP. SBMA
Location/Address: Boton SBMA
Contract Time: 70 days
Date Start: June 01,2005
Date Completed: August 11,2005
|
completed |
FAMILY VILLE-PHASHE 2 ROAD NETWORK
Client: LAUS GRPOUP OF COMPANIES
Location/Address: Lubao, Pampanga
Contract Time:60 Working days
Date Start: Sept. 2004
CONSTRUCTION OF MULTI-PURPOSE BLDG.
Client: DPWH, District # 1
Location/Address: Parian, Mexico,Pampanga
Contract Time: 120 days
Date Start: August 16,2004
Date Completed: October 24,2004
|
completed |
ELEVATED 2 CLASSROOM SCHOOL BUILDING.
Client: PAMPANGA PROVINCIAL CAPITOL
Location/Address: Bitas, Arayat, Pampanga
Contract Time: 60 Working days
Date Start: April 05, 2002
Date Completed: May 15, 2002
|
completed |
FARM TO MARKET ROAD ( SAN LORENZO ,MEXICO)
RENOVATION OF DAY CARE CENTER (SAN ROQUE,
ARAYAT)
RENOVATION OF STAGE (LAPUT, MEXICO)
Client: PAMPANGA PROVINCIAL CAPITOL
Contract Time: 60 Working days
Date Start: June 07 ,2002
Date Completed: July 02, 2002
|
completed |
COMPLETION OF PUBLIC MEXICO PUBLIC MARKET
Client: PAMPANGA PROVINCIAL CAPITOL
Location/Address: Town Proper, Mexico Pampanga
Contract Time: 180 days
Date Start: October 18, 2002
Date Completed: January 08, 2003
|
completed |
UPGRADING OF SAN JUAN MEXICO BRGY. ROAD
Client: PAMPANGA PROVINCIAL CAPITOL
Location/Address: San. Juan, , Mexico, Pampanga
Contract Time: 30 days
Date Start: September 03, 2003
Date Completed: September 12 , 2003 |
completed |
| |
|
|
|